Crude oil flowing from Canada to Texas refineries

Share on Twitter Share on LinkedIn
Staff writer ▼ | January 27, 2014
TransCanada reported that the Gulf Coast Project began delivering crude oil to Texas refineries. The completion of this $2.3 billion crude oil pipeline provides a direct connection between the important oil hub in Cushing, Oklahoma and delivery points on the U.S. Gulf Coast.
TransCanadaTransCanada reported that the Gulf Coast Project began delivering crude oil to Texas refineries. The completion of this $2.3 billion crude oil pipeline provides a direct connection between the important oil hub in Cushing, Oklahoma and delivery points on the U.S. Gulf Coast.


Construction of the 487-mile crude oil pipeline involved more than 11 million hours of labor completed by 4,844 workers in the United States of America, more than 50 contracts with manufacturers and companies building the pipeline and equipment from across the U.S. It also includes the addition of 2.25 million barrels of new oil storage capacity at Cushing, Oklahoma.

The Gulf Coast Project was designed to help relieve the glut of crude oil in places like Cushing, Oklahoma and will transport growing supplies of U.S. supply to meet refinery demand. It provides Gulf Coast refineries with access to lower cost domestic production and reduces America's reliance on foreign sources of crude oil.

In addition, the standards that TransCanada adopted for the Gulf Coast Project have set a new bar for safety and design of modern crude oil pipelines. This includes a higher number of remotely controlled shutoff valves, increased pipeline inspections, increased standards for pipeline construction, maintenance and integrity, and burying the pipe deeper in the ground.

The U.S. is the largest oil consumer in the world and uses 15 million barrels of crude oil every single day. The latest data shows that about half of that is imported. Even with growing U.S. production and increasing fuel efficiency standards, the International Energy Agency and the U.S.'s own Energy Information Administration forecast the need for between four to six million barrels of imported crude oil a day until 2040.

The Gulf Coast Project is a 487-mile (780-kilometer), 36-inch crude oil pipeline beginning in Cushing, Oklahoma, and extending south to Nederland, Texas, to serve the Gulf Coast marketplace. The Gulf Coast Project will have the initial capacity to transport up to 700,000 barrels of oil per day with the potential to transport up to 830,000 barrels of oil per day to Gulf Coast refineries. TransCanada is currently projecting pipeline capacity of 520,000 barrels per day for the first year of operation. For more information, please visit Gulf-Coast-Pipeline.com.

The 48-mile (77-kilometer), Houston Lateral Project is an additional project under development to transport crude oil to refineries in the Houston area. All permissions necessary to the project are in place and construction is underway on the project.